Everett Average Citizen
Everett Average Citizen
Home | Profile | Register | Active Topics | Active Polls | Members | Private Messages | Search | FAQ

 All Forums
 Community
 Community Meetings
 Public Hearing/Lower Broadway

Note: You must be registered in order to post a reply.
To register, click here. Registration is FREE!

Screensize:
UserName:
Password:
Enter Anti SPAM Code: Please enter this code in the box below. If you cannot read it refresh the page. Click here for more detailed instructions.Play Sound
Click here to refresh this page
Format Mode:
Format: BoldItalicizedUnderlineStrikethrough Align LeftCenteredAlign Right Horizontal Rule Insert HyperlinkInsert EmailInsert Image Insert CodeInsert QuoteInsert List Insert youTube videoInsert Windows Media AudioInsert Windows Media VideoInsert Macromedia FlashInsert Google Video
   
Message Icon:              
             
Message:

* HTML is OFF
* Forum Code is ON
Smilies
Smile [:)] Big Smile [:D] Cool [8D] Blush [:I]
Tongue [:P] Evil [):] Wink [;)] Clown [:o)]
Black Eye [B)] Eight Ball [8] Frown [:(] Shy [8)]
Shocked [:0] Angry [:(!] Dead [xx(] Sleepy [|)]
Kisses [:X] Approve [^] Disapprove [V] Question [?]

 
   

T O P I C    R E V I E W
tetris Posted - 07/13/2009 : 12:02:53 PM
http://www.mhd.state.ma.us/default.asp?pgid=content/hearings/everett_071409&sid=hearing

Notice of a Public Hearing

A Design Public Hearing will be held by MassHighway (Project# 602382) to discuss the proposed reconstruction and signal improvements in Everett and Boston, MA.

WHERE:

City of Everett
City Hall
Keverian Room, 3rd Floor
484 Broadway
Everett, MA 02149

WHEN:

Tuesday July 14, 2009 at 7:00 P.M.
#65532;

PURPOSE:

The purpose of this hearing is to provide the public with the opportunity to become fully acquainted with the proposed Reconstruction and Signal Improvements on Route 99. All views and comments made at the hearing will be reviewed and considered to the maximum extent possible.

#65532;
PROPOSAL:
This project consists of reconstruction and signal improvements on route 99 (Broadway), from Sweetser Circle to Aifrod Street Bridge. These improvements include: pavement overlays, minor drainage improvements, sidewalk and ramp accessibility improvements, signal improvements, a 4 foot shoulder in the south-bound direction, and a 15 foot outside travel lane in the north-bound direction to accommodate bicycles.

A secure right-of-way is necessary for this project. Acquisitions in fee and permanent or temporary easements may be required. The Cities of Everett and Boston are responsible for acquiring all needed rights in private or public lands. MassHighway#65533;s policy concerning land acquisitions will be discussed at this hearing.

Written views received by MassHighway subsequent to the date of this notice and up to five (5) days prior to the date of the hearing shall be displayed for public inspection and copying at the time and date listed above. Plans will be on display one-half hour before the hearing begins, with an engineer in attendance to answer questions regarding this project. A project handout will be made available on the MassHighway website listed below.

Written statements and other exhibits in place of, or in addition to, oral statements made at the Public Hearing regarding the proposed undertaking are to be submitted to Frank A. Tramontozzi, P.E., Chief Engineer, Massachusetts Highway Department, 10 Park Plaza, Boston, MA 02116. Such submissions will also be accepted at the hearing. Mailed statements and exhibits intended for inclusion in the public hearing transcript must be postmarked within ten (10) business days of this Public Hearing.

The community has declared that this facility is accessible to all in compliance with the ADA / Title II. However, persons in need of ADA / Title II accommodations should contact Angela Rudikoff by phone VOICE (617) 973-7005, TDDY (617) 973-7306 or email angela.rudikoff@eot.state.ma.us. Requests must be made at least 10 days prior to the date of the public hearing.

In case of inclement weather, hearing cancellation announcements will be posted on the MassHighway website http://www.mass.gov/mhd.
15   L A T E S T    R E P L I E S    (Newest First)
turk182 Posted - 09/18/2009 : 2:58:21 PM
Another case of Wag the Dog.




''Life's tough......it's even tougher if you're stupid.''
-- John Wayne
carlost everett Posted - 07/19/2009 : 07:40:37 AM
Of course nothings down there. Thibeault and the Mayor are complying at that location so they can make a compelling arguement to city government to relocate to south Everett. Funny thing is; they'll buy it. Pathetic!
Paul Posted - 07/18/2009 : 11:33:05 AM
Thanks Tetris I am going to take a look at the document/maps you have referenced.

I took a ride down to Wood Waste yesterday and it appears almost everything is gone from there.
Cruller DaVille Posted - 07/17/2009 : 4:35:02 PM
So they are modifying or trading one project for another, interesting. Thanks for the update Tetris. Whichever proposal they chose and whatever way you slice it, that road has been in desperate need of revamping for at least two decades. I bet the number of cars that have been swallowed up by Route 99 near one thousand.

I cannot believe that any part of Mr T's plan would be conducive to the forward promoting Urban Ring's plans. Sure, the pant full of bull plans that they waved in front of us a few years ago including a marina and hotel but the "actual" plans whereby Wood Waste is relocated and nestled right on Boston Harbor's edge and simultaneously abutting the railroad tracks.... I cant even phathom that being considered. However, who can tell what will happen when mega bucks change hands. DEP, Boston Conservation Commission and the Harbor groups should all stand up and holler when those plans reach their eyes.... However, we all know how that goes so who truly knows what will happen.

Scary how the democratic process reverses itself in this city and what we all want is not what we get.

Just MY Humble Opinion....


"Cruller DaHville"
tetris Posted - 07/17/2009 : 11:30:02 AM
Paul,

I didn't hear anything about Wood Waste coming up. I'm sure I would have if it did. The issue of trucks going to the sludge plant did though; nothing new, just the additional traffic concern.

As far as Wood Waste going to lower Broadway, the Urban Ring data I found yesterday caused me to have a new thought. For this access, they will need a right of way over the lower Broadway parcel for the modified access. If you look at the maps included in the document I referenced in my prior post, it appears that the access they are suggesting could go right thru the area that was proposed for relocating Wood Waste. Again, those plans are far from final but it look like Thibeault could profit big time from this, on the tax payer dime no less, and also improve the access to the remainder of the parcel. Maybe that helps to explain why, other than the sweetheart deal from Restaurant Depot, the plans to have something on a grander scale on the parkway were dropped and Wood Waste may actually remain where it is. Just a thought though.
tetris Posted - 07/17/2009 : 11:08:20 AM
If you look at the entire document (https://www.commentmgr.com/Projects/1169/docs/NPC_Final_fixed_06-30-09.pdf) Crueller, you'll see that the Sulivan/Assembly Square/Wellington link is being eliminated in favor of this new route. Just a warning though, the document is rather larger and takes a while to download. The project is still in a conceptual design phase so who knows what the final design will ultimately include.

From what I heard, most of the elected officials (and candidates) that spoke were pretty adamant about the need for at least a blinking traffic light with on-demand walk cycle at Thorndike Street. As far as being on point, well that depends on how you look at the project. The project team thought that they were for presentation on a reconstruction project; what they got was an earful on all of the traffic issues in the area. That was more from the residents than the elected officials though but it forced politicians to get involved as well.

As I previously mentioned, the Mayor had left the meeting by that point; the Community Development Director was gone by then too leaving the Engineering Department holding the bag and they didn't have the answers people were looking for. When the Mayor had spoken earlier, he ended his brief comments talking about new lighting and banners. Take that for what you will.

Tails, to answer a couple of your questions, I heard that the subject of the building at the corner of Beacham did come up. Mass Highways would have liked to see that building come down. However, it would have been the city's responsibility to acquire the property and they didn't want to do it. As far as the Tobin goes, the issue of giving Everett residents a discount did come up. Control of the bridge may change from Massport to Mass Highways. If that were to occur, Mass Highways said they would at least consider the possibility; but, if Massport retained control, they admitted that they doubted that it would ever happen.

I wish that ECTV had covered the meeting. Seems just as, if not more, important than some of the other things they cover.
Paul Posted - 07/17/2009 : 10:20:08 AM

TETRIS

Was anything about Wood Waste brought up at the meeting by the residents of South Everett?

THANKS!
Tails Posted - 07/17/2009 : 09:26:45 AM
I thought that whole area was being redesigned from the rotary down to Beecham St? Then at Beecham St, they were going to knock out the building and widen the road. Part of this project was to alleviate the traffic mess in that area, especially around the rotary. Just repaving is not going to do that. I realize it’s the state’s project but we were told one thing, and now it sounds like we are getting something else.

I agree the administration needs to take an aggressive role and demand that. Don’t forget, we have been threatened by the Governor to double the fees on the Tobin. If the Governor gets his way, it would be a grid lock nightmare and back up traffic for miles all over Everett. Demand accountability now, and by the way………the administration should make this info more assessable to the public. ALL citizens of Everett will be affected by this project and have the right to proper notification.
Cruller DaVille Posted - 07/17/2009 : 08:08:51 AM
That proposed redesign et al of Sullivan to Wellington was an agressive plan/project Curtatone and McGlynn have been pushing for quite some time. I think that may be independent of the Broadway 99 project, but who knows.....

South Everett has long had issues with 99 and I agree with Tets and Tails that the repaving aspect may not be the real solution there. Those potholes and water run off scream for redesign, but alas, state projects are notoriously ill conceived and slapped together unless the municipality takes an agressive role.

Tets... were our elected officials animated and on point during the public hearing?




"Cruller DaHville"
tetris Posted - 07/16/2009 : 10:29:38 PM
I heard Keith Spencer from the Independent was there so maybe we'll get some additional info in the Independent next week. No ECTV though.

One thing that I forgot though. The project will require a number of temporary rights of way during the construction period. All of these must be acquired before construction can begin. If payment is necessary to acquire them, that's the city's responsibility.
Tails Posted - 07/16/2009 : 10:11:36 PM
S/B interesting. I hope this gets brought up with the city council when they get back in session so everyone can know what's going on.
tetris Posted - 07/16/2009 : 9:44:19 PM
In a related note, I found the following information today in a recent Notice of Project Change document for the Urban Ring project:

Mystic River Crossing:

Everett – Sullivan Square. Instead of traversing the Revere Beach Parkway – Wellington Station – Route 28 – Assembly Square alignment included in the RDEIR, the revised alignment would continue south along the Newburyport/Rockport commuter rail corridor, pass over or under the commuter rail line in the vicinity of Chemical Way, cross the Mystic River in mixed traffic on Route 99, and connect to Sullivan Square via bus-only roadways segments that are currently under study by the City of Boston.

As far as I know, this wasn't discussed at the public hearing the other night.
tetris Posted - 07/16/2009 : 9:08:40 PM
From what I've heard, there were a lot of people from South Everett there (seats were full when the meeting started) and they weren't particularly happy. They may not have had the time to mobilize properly because the local papers that the notice appeared in aren't delivered to that part of the city. They only became aware of it because one of the Ward 1 councilors notified them at some point.

A few of the high (low?) lights I heard:

- Not a full depth reconstruction, just repaving, except at spots (intersection of Broadway and Beacham, other areas they may find after removing the pavement) that need it. I think I was told that the repaving would include additional material to bring roadway up an inch.

- Two foot widening of road in Everett, accomplished by reducing the sidewalk width on the north bound side of the road.

- No real dedicated bike "lane"; rather an expansion of the shoulder to better accomodate bikes. Bike people not happy.

- No signal planned at Thorndike Street. A lot of people that spoke found that unacceptable. Project still in design phase; they'll look at it. (Please don't shoot the messenger.)

- Lots of discussion about traffic patterns in the area. Discussions really went nowhere. Mass Highway needs to work with the city on these issues but the city is primarily responsible for these. A couple of times, the people in the room turned towards where the mayor was sitting looking for answers but he had left the meeting by then.
Cruller DaVille Posted - 07/16/2009 : 4:33:53 PM
I'm truly surprised that the old South Everett group wasn't remobilized for the event. This is truly the beginning of alot of changes in the area and I couldn't agree with Tails more, the stage is being set for everything WW wants.
Everett is truly going down the hopper. Who knows what two more years of this kind of corrupt, unresponsive government is going to bring us.

Just MY humble opinion


"Cruller DaHville"
Tails Posted - 07/15/2009 : 8:06:27 PM
No, Wood Waste did not have anything to do with the hearing. However, I feel it can, in essence, impact the reconstruction project.

Of course for many, many reasons..... that's not an area where Wood Waste should go and we are going to finally have a nice brand new road, with new sidewalks, a bike path...... to an area that is LONG overdue. Lower Broadway is also the gateway to Everett.

That's not fair having Wood Waste there - that spews everything and anything into the air and their trucks .........to an area that's already truck burdened. Wood Waste was not relevant to the hearing, but I think it should be.

The reason it was brought up at all was because the word is the Wood Waste owner signed an 11 Million dollar deal in Everett. What else could it possibly be, if not lower Broadway?

Everett Average Citizen © 2000-05 ForumCo.com Go To Top Of Page
This page was generated in 1.69 seconds. Snitz Forums 2000
RSS Feed 1 RSS Feed 2
Powered by ForumCo 2000-2008
TOS - AUP - URA - Privacy Policy